2025-06-10 00:00:00
Press release
Battery Installation Completed, FIP Operations Begin at Nagasaki Power Station
TOUCHI INTERNATIONAL CORP. has completed the installation of a battery storage system, constructed and introduced by OMRON Corporation, at its solar power plant located in Nagasaki Prefecture. Full-scale operation under the Feed-in Premium (FIP) scheme will commence in June 2025.
2025-02-20 00:00:00
Press release
Battery Installation Work Begins at Nagasaki Power Station
TOUCHI INTERNATIONAL CORP. has commenced construction of a battery storage system at its solar power plant in Nagasaki Prefecture, aiming to effectively utilize renewable energy. The project is scheduled for completion in the first half of 2025.